Status note: EPA’s Lead and Copper Rule Improvements (LCRI) are being challenged in AWWA v. EPA in the D.C. Circuit, which heard argument on September 30, 2026. As of this writing, no decision has been reported, and EPA has said it will defend the rule. The dates below are the rule as written. Check for a ruling before you plan around them.

Quick answer

Starting November 1, 2027, most U.S. water systems must begin replacing every lead and galvanized-requiring-replacement service line in their system, generally within 10 years, by December 31, 2037. That’s millions of lines, and a lot of it is plumbing work: the customer side of the line, the connection inside the house, and the permits and restoration that come with it.

  • Full replacement only. Partial replacements are limited to emergencies and planned capital projects and don’t count toward a utility’s replacement rate.
  • The utility runs the program, but must offer to hire the contractor and coordinate customer-side work. That’s where plumbers come in.
  • Lead action level drops from 15 ppb to 10 ppb on November 1, 2027.
  • Federally funded jobs carry Davis-Bacon prevailing wage and Build America, Buy America requirements.
  • EPA’s average cost estimate is $4,700 per full replacement, with a range of $1,200 to $12,300.

Lead service line replacement is the biggest steady stream of residential water-line work coming to the plumbing trade in a generation. EPA estimated in late 2025 that about 4 million lead lines remain. The federal rule that forces their removal starts its clock on November 1, 2027, and utilities are already building inventories and lining up contractors. Here’s what the rule requires, where plumbing contractors fit, and what it takes to get the work.

The LCRI timeline

DateRequirement
October 16, 2024Initial service line inventories due (under the earlier 2021 rule)
Each November, 2025–2027Annual notices to customers with lead, galvanized-requiring-replacement, or unknown lines
November 1, 2027LCRI compliance date: baseline inventory, replacement plan, and school and child care lists due; lead action level drops to 10 ppb; 10-year replacement clock starts
End of 2034Non-lead validation of unknown lines
December 31, 2037End of the standard 10-year replacement period for most systems

Sources: EPA LCRI documents as compiled by LeadPipeHelp and CDM Smith’s LCRI FAQ. Some systems may qualify for deferred deadlines under the rule.

The rules that shape the work

Full replacement, not partial

The LCRI limits partial replacements, where only the utility side or only the customer side is replaced, to emergency repairs and planned capital improvement projects. Partials can’t be part of a replacement program, don’t count toward the required replacement rate, and leave the line classified as lead. When a partial happens in an emergency, the utility has to offer to replace the customer side within 45 days, and provide flushing instructions, six months of filters, and follow-up sampling.

For plumbers, that means most program work is full-line: main to meter to house, including the customer side that has historically been the homeowner’s problem.

Customer consent and cost

Connectors and galvanized lines

Where plumbers fit

PathWhat the work looks likeWhat it takes
Utility prime contractsBatches of hundreds of addresses, full-line replacement, restorationPublic bidding, bid, performance, and payment bonds, excavation crews, right-of-way permits
Subcontracting to a primeCustomer-side and in-house connections for a large general or utility contractorState plumbing license, insurance, certified payroll, capacity to run several crews
Homeowner-paid customer sideHomeowners replacing their side where the utility won’t pay, or getting ahead of the programPlumbing license, permit, coordination with the utility on timing
Inspection and identificationVerifying material at the meter and where the line enters the houseTraining on identification methods; some utilities hire plumbers for verification

Source: VendBuddy’s guide to lead service line replacement contracting.

The interior connection is often the part utilities and excavation contractors least want to do: getting through the foundation wall, setting a new meter or valve, and tying into existing plumbing that may itself be galvanized or old. That’s plumbing work, and it’s where licensed shops have the edge.

Funding, prevailing wage, and BABA

States with their own deadlines

Several states moved before the federal rule and set their own timelines, which can be faster. Michigan’s 2018 rule requires replacement of lead lines over roughly 20 years; New Jersey’s 2021 law requires replacement within about 10 years; Illinois’s Lead Service Line Replacement and Notification Act sets timelines that scale with the number of lead lines a system has, with Chicago on the longest schedule. Check your state drinking water program for exact dates, cost-sharing rules, and whether homeowners can be charged.

Field work: identification, replacement, and safety

Identifying the line

Many utility records are wrong or incomplete. Field identification usually means checking the line at the meter and where it enters the building, and potholing to confirm material. Signs a plumber already knows: lead is dull gray, soft enough to scratch to a shiny silver with a key, and doesn’t attract a magnet. Galvanized steel is magnetic; copper scratches to a penny color.

Replacement methods

Safety

Homeowners who call you first

As utilities send annual notices, homeowners will call plumbers asking whether their line is lead and whether they should replace it now. A good answer:

How to get ready

☐Find your local utilities’ inventories and replacement plans, and when they’re bidding.
☐Register as a vendor with utilities and the large contractors likely to win prime contracts.
☐Get bonding capacity in place if you want to bid as a prime.
☐Set up certified payroll for Davis-Bacon jobs.
☐Confirm BABA-compliant suppliers for pipe, fittings, and meter setters.
☐Train crews on identification, trenching, and lead exposure.
☐Build a documentation routine: before and after photos, materials, addresses.
☐Watch for the D.C. Circuit decision in AWWA v. EPA.

Program work is volume work: hundreds of addresses, crews in different neighborhoods, and documentation the utility needs for every one. VortechPro keeps every job, address, and record by crew. $99/mo for 5 techs, +$20 each.

Run hundreds of addresses without losing track

VortechPro for plumbing contractors: dispatch and job records by crew. $99/mo for 5 techs, +$20 each. 30-day free trial, no contract.

FAQ

When do lead service lines have to be replaced?
Under EPA's Lead and Copper Rule Improvements, most water systems must begin complying on November 1, 2027, and replace lead and galvanized-requiring-replacement service lines generally within 10 years, by December 31, 2037. Some systems may qualify for deferred deadlines.
Is the LCRI being challenged in court?
Yes. The American Water Works Association challenged the rule in the D.C. Circuit in AWWA v. EPA, which heard oral argument on September 30, 2026. EPA has said it will defend the rule while developing implementation flexibilities.
Are partial lead service line replacements allowed?
Only in limited cases. The LCRI limits partial replacements to emergency repairs and planned capital improvement projects, and partials don't count toward a utility's replacement requirement. After a partial, utilities must provide flushing instructions, six months of filters, and follow-up sampling.
Who pays for replacing the customer side of a lead line?
The federal rule doesn't require the utility to pay for the customer side if grants or loans don't cover it, but the utility must offer to hire the contractor and coordinate the work. Some states bar charging homeowners or provide funding.
What is the new lead action level?
The LCRI lowers the lead action level from 15 parts per billion to 10 parts per billion, effective November 1, 2027.
Do lead line replacement jobs require prevailing wage?
Projects funded through the Drinking Water State Revolving Fund carry federal Davis-Bacon prevailing wage and certified payroll requirements, along with Build America, Buy America sourcing rules for iron, steel, and manufactured products.
How much does lead service line replacement cost?
EPA's average estimate for a full replacement is about $4,700, with a range of $1,200 to $12,300, depending on length, depth, restoration, and local conditions.
How can you tell if a service line is lead?
Lead pipe is dull gray, scratches easily to a shiny silver, and won't attract a magnet. Galvanized steel is magnetic, and copper scratches to a penny color. Many utilities also publish searchable service line inventories.